By Ignatius Chukwu
As power supply returns to Bayelsa State, communities along power lines may become the first line of charge for protection of sensitive equipment.
This is as the Transmission Company of Nigeria (TCN) says it has restored bulk power supply via Ahoada-Yenagoa 132kv Line following replacement of vandalized towers
The TCN said the light was restored at 08:03am on November 30, 2024. This is said to follow successful reconstruction of collapse towers and restringing of vandalized conductors by TCN contractors. Sources in Bayelsa State said there was huge jubilation when light returned in the state after about four months.
Sources added that over 150 transformations were vandalized and that the state government replaced them all for TCN to take action, else the state would remain in darkness. This has raised eyebrows how government would continue building projects for citizens to vandalize.
Now, TCN said a final inspection (of work done) was conducted on November 28, 2024, by a team of TCN engineers led by the Port Harcourt region General Manager, Engr. Emmanuel Akpa. The team verified the integrity of the 20 newly erected towers (Nos. 48-64 and 97-99) that were destroyed in series of vandalism incidents of July 29 – August 12, 2924. After confirming that all work met required standards, the line was cleared for energization.
On the other hand, discussions are underway with stakeholders in Bayelsa and Rivers states to implement a comprehensive community engagement programme. The initiative seeks to educate the local communities traversed by the transmission line on the consequences of vandalism and theft of power infrastructure.
Additional, the programe will involve appointing community representatives to oversee the security of power equipment in their areas. The approach aims to foster a sense of local ownership and accountability for the infrastructure.
These efforts are part of broader measures to prevent future incidents of large -scale vandalism, which left Bayelsa State in total blackout since July 29, 2024. The economic losses incurred by residents, as well as the significant financial burden on TCN to restore the tower, have been substantial.
TCN appeals to the public to support the nationwide campaign against the vandalism of power infrastructures. Collective action is essential to safeguarding the country’s electricity assets for sustainable development.
(Source: Ndidi Mbah, GM, Public Affairs)
$$